Project timeline
Once the client confirms his willingness to acquire a plant, we structure the work in the following steps:
Once the client confirms his willingness to acquire a plant, we structure the work in the following steps:
1
1
We collaborate with the client in defining the critical data of their project:
- Plant size
- Products to be produced
- More convenient location based on proximity to product consumption and availability of supplies.
2
2
We guide the client in terms of investment costs (CAPEX) and operating costs (OPEX) that they will have with the new plant.
Once the corresponding contracts are signed:
3
3
We started a fast-track project process, where AVS and the client work simultaneously and in coordination, with the aim of having the plant producing in a period of 18 to 24 months, depending on its size. This process includes:
- We deliver to the client the FIRST engineering PACKAGE, which will allow them to apply for environmental permits.
- We started the construction of the modules in the AVS workshops in Uruguay.
- We deliver the SECOND PACKAGE of engineering for the client to start civil and electrical engineering on-site.
- We deliver the THIRD engineering PACKAGE for the client to apply for construction permits.
- We deliver the FOURTH PACKAGE of engineering, at the same time that the client will be quoting and selecting the supply of the civil and electrical works.
- The client solves the power supply.
- The client begins the civil construction that will take approximately 6 months.
- The modules built in Uruguay are shipped to the site and arrive with more than half of the civil works carried out.
- The installation and interconnection of the modules and external equipment begins.
- The electrical installation is completed, including a substation for power supply.
4
4
AVS trains operators, performs pre-commissioning, commissioning and start up of the plant.
5
5
The performance test is carried out that verifies the promised production.